I'm setting up a new plan and was entering a constraint for a milestone. I entered the constraint as the same date and time as the scheduled end date.
A violation popped up. When I clicked on it, one of the potential resolutions was to move the constraint back to match the end date! I tried clicking that option, but the violation will not clear.
I've attached a screenshot of the violation pop up next to the task information inspector.
Any insights would be appreciated by this newbie!
A violation popped up. When I clicked on it, one of the potential resolutions was to move the constraint back to match the end date! I tried clicking that option, but the violation will not clear.
I've attached a screenshot of the violation pop up next to the task information inspector.
Any insights would be appreciated by this newbie!