leveling for non-fulltime resources? Thread Tools Search this Thread Display Modes
Hi everyone,

I have seen multiple forum posts with questions about leveling and units < 100%, but haven't found the answer I was looking for. I am using Omniplan 2.1.2.

My example:
- two tasks: Start (1d) and Finish (6d)
- resource group "my team" with John and Mary
- resources are set to "keep effort fixed"
- the team works part-time (50%)
- I assign the tasks to "my team"

To specify the resources are working part time, I have set their units to 50%.
They don't have fixed schedules, all I know is that they work 20 hours a week.

When I level my project, each task is done both by John (50% of 50%) and Mary (50% of 50%).

This is not what I expect. I would expect only one person to work on the task, and automatically adjust the duration if necessary.

Any suggestions?
 
When you make the assignment, OmniPlan by default tries to get 100% units assigned to it. In your case it's able to grab two resources to achieve that. If you select the tasks, hop over to the Task: Assignments inspector and set the "Assigned amount" of the group to 50% you'll get what you want.

-Tom
 
Thanks Tom. In some cases it makes sense to get 100% units assigned. In other cases it does not as the task needs to be finished by the same person that started it. E.g. "read a book", or "walk from A to B".

Assigned amount limits it by task, I would like the amount to automatically depend on the selected resource. But that would then be for a future version of Omniplan I guess. :-)
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Untitled task in resources view after undo leveling luke18 OmniPlan General 4 2011-09-08 10:11 AM
I just don't understand leveling and <100% resources schmidt4brains OmniPlan General 6 2010-06-20 08:50 AM
Leveling leaves resources overused granerw OmniPlan General 4 2008-02-27 09:49 PM
Leveling resources connie OmniPlan General 1 2006-08-22 05:10 PM


All times are GMT -8. The time now is 04:01 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.