I know that OG is busy with OP on the iPad but it would be nice to finally have these bugs fixed, some of them half a year since notification. Maybe at least some comments about their status? (The PDF layout bug seems simple to fix to me, but maybe not?):
plus very useful and helpful feature requests:
Best regards,
Michael
- Bug in filter subsystem (dependency chain filter working depends on showing it in group tasks or flat list)
- a MPP milestone is not imported as a milestone but a 0-day
task (i know you are working on a new importer, any beta test soon?)
- PDF export respects wrongly the height of uncollapsed lines, even so only the Gantt chart should be produced, producing a very low density Gantt chart with odd heigh lines.
- Drawing of dependency lines look cluttered due to overlayed date string drawing (the date separator interrupts the dependency line)
- Project->Catch Up to Date (Or toolbar button 'Update completion of tasks to a certain date) does not update milestones (bug or feature?).
plus very useful and helpful feature requests:
- OP to remember the last
state of the checkbox 'Only update selected items' for the dialog
'Update completion of tasks to a certain date'.
- Include 'Do NOT match' filter criteria
Best regards,
Michael