HowTo: Dependency on % Completion instead of date or actual complete? Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Hi All,

Apologies if this has been answered already elsewhere. Is there a way to set a task dependency (or, more appropriately, constraint) whereby a task cannot start until a preceding task reaches X% completion?

Essentially I have a situation where I have task2 dependent upon task1 (theoretically), however work may actually commence on task2 provided that task1 has reached a minimum of 75% completion. Needless to say, task 2 cannot end prior to task1 completion, of course.

Is there a way to do this?

Thanks in advance,


Leland
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Query based on completion date cdavaz OmniFocus 1 for Mac 3 2012-07-17 09:20 AM
howto: date AND time via email Vlad Ghitulescu OmniFocus 1 for Mac 0 2011-04-30 12:20 AM
Due Date Deletion Triggers Completion EricW OmniFocus 1 for Mac 0 2008-02-19 02:04 AM
Date of Completion? dhm2006 OmniFocus 1 for Mac 2 2007-07-18 08:33 AM
Address completion by date? ata OmniWeb Feature Requests 4 2007-02-17 10:07 AM


All times are GMT -8. The time now is 12:46 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.