Is there a way I can automatically set a project start date based on the completion of another project?
  Reply With Quote
Not directly that I know. One way I might handle this is to put a concluding task in the first project that says something akin to "initiate second project". I would then link to the second project using the notes field of this task, and I would put the second project On Hold until the final task of the first project is completed.

--
JJW
  Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Start Date On Project Line Problem Teresa_H OmniFocus 1 for Mac 2 2010-09-11 11:28 AM
Project Start date query james_drury OmniPlan General 2 2010-07-30 10:05 AM
Change Project start date? paulriedel OmniPlan General 2 2009-12-09 01:55 PM
Project Start Date Issues Joshu OmniFocus 1 for Mac 1 2008-08-04 10:28 AM
Question: Auto Start Date Option? oschultz OmniFocus 1 for Mac 5 2007-11-29 01:52 PM


All times are GMT -8. The time now is 10:13 AM.


Powered by vBulletin® Version 3.8.6
Copyright ©2000 - 2013, Jelsoft Enterprises Ltd.