easiest way to determine whether enough resources exist for a project Thread Tools Search this Thread Display Modes
In Omniplan, what is the easiest way to determine whether enough resources exist for a project ?

In other words, for a set of tasks being done on a given day, I would like to know if I have enough resources to do the tasks...
What is the easiest way to accomplish this ?

tx,
/Fernando
 
Have you looked at the resource utilization view (View->Resource View)? That will show if any resources are overcommitted, as seen in the attached example. Note that leveling the project will tend to undo any overcommitments unless there are enough constraints to force a particular solution. Without the constraints on the example, leveling would spread the tasks over 3 days.
Attached Thumbnails
Click image for larger version

Name:	Screen shot 2010-03-19 at 9.15.07 PM.png
Views:	714
Size:	77.5 KB
ID:	1318   Click image for larger version

Name:	Screen shot 2010-03-19 at 9.15.23 PM.png
Views:	676
Size:	42.5 KB
ID:	1319  
 
Thanks.
This helps, but it is "resource centric".
I am looking for a single location where I can see the sum of resources compared to the sum of resources needed.

Using a spreadsheet, this could be done by summing values of cells representing each resource needed and then comparing it with the overall resources available...

tx,
/Fernando
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Set new date for action - Easiest way? carlsson Applying OmniFocus 2 2011-07-08 01:54 PM
Resources only available for a project part of the time jackbaty OmniPlan General 2 2010-09-21 06:51 AM
Project crashes everytime when I level resources across all tasks mspeer OmniPlan General 1 2009-01-02 08:07 AM
Easiest way of setting up OmniFocus on 2 machines? fmantek OmniFocus 1 for Mac 2 2007-12-06 09:08 AM
Dashboard for viewing taks/resources as the mouse hovers over the project period mr_projects OmniPlan General 0 2007-10-31 02:27 AM