Shouldn't a Next Action with Future Start Date = Pending Project? Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
If I have a sequential project whose next action has a future start date, would this not be a "Pending Project"?

Right now, Omnifocus shows these projects as active, but there's nothing you can do with it until a date in the future because there are no available actions. My workaround has been to copy and paste the next actions's start date to the project's start date. The project will then show up as "Pending".

I'm guessing, is the logic for the current implementation so projects don't disappear to Pending status when the project itself is technically active even though you can't do anything with it?

Cameron
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Add the ability to hide project folders with no content or future start dates Kosjer D OmniFocus 1 for Mac 1 2012-02-03 07:32 AM
Unwanted Loc. reminders now for an action due in Jan [A: add start date to action] jman995x OmniFocus for iPhone 4 2011-12-01 01:39 PM
Set Action B's Start Date to Action A's Completion Date ankushnarula OmniFocus 1 for Mac 1 2009-02-23 07:28 AM
Projects are stalled if they have an action with a future start date SpiralOcean OmniFocus 1 for Mac 11 2008-04-02 02:00 PM
Bug: single tasks with start up date in the future brab OmniFocus 1 for Mac 0 2007-06-05 12:58 AM


All times are GMT -8. The time now is 11:25 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.