Leveling Not Working Correctly Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I've attached two images to this message.

As you can see, in the "before" image (Picture 1) I have tasks assigned to the same resource overlapping. This is because they are partially done (they were done out of order) and the tasks are lined up with the incomplete portion of one task starting when the previous task ends. Lining the tasks up this way is the only way I can see to get an estimate for when all the tasks will be done.

Now see the "After" image (Picture 2). Lining tasks up one after the other, NOT taking into account which tasks are partially complete (as is done by the Level command) means that my estimate for when the series of tasks will be complete is greatly expanded. It does NOT take four additional days of work to finish a four-day task that is 75% completed, it takes one additional day of work.

Is there another way of solving this problem? Am I missing something in the program? Or do I need to wait for the next version?


Thanks very much!


John
Attached Thumbnails
Click image for larger version

Name:	Picture 1.png
Views:	780
Size:	12.7 KB
ID:	73   Click image for larger version

Name:	Picture 2.png
Views:	801
Size:	12.3 KB
ID:	74  

Last edited by schof; 2006-08-01 at 12:42 PM..
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Text of Objects not appearing correctly mtennes OmniGraffle for iPad 0 2013-03-07 06:59 AM
Duration not adding up correctly rianquinn OmniPlan General 0 2011-10-20 05:46 AM
Web colours not working correctly in OmniWeb? Steeve OmniWeb General 7 2009-04-01 02:59 AM
Changes not syncing correctly between computers beharkey OmniFocus Syncing 6 2008-08-01 12:32 PM
Effort not summing correctly? RedCoat OmniPlan General 3 2008-03-03 01:48 PM


All times are GMT -8. The time now is 10:09 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.