Dragging/changing task durations. Thread Tools Search this Thread Display Modes
I'm trying to drag task durations (i.e. changing the completion date by dragging the handle at the end of the task bar), and am getting extremely frustrated by what appears to be a bug:

If I drag a task at the end of my project to an earlier date, the range of dates reduces to match - fair enough I guess.

But if I've gone too far back, or just want to drag forward in time, the available dates won't expand. So for example if the last date on show is 21/11/2007, I can't drag to 30/11/2007. Arrrggghh.

Also, it's not always possible to grab the dependancies handle at the end of the last task - the handle disappears before I get to it.

Is this a bug, or am I missing something?

Mark
 
Hi Mark,

not a bug as such, I am a fairly new user my self but the behavior is a little "odd" you just have to have the mouse pointer in just the right position to advance past the "currently last entry", i find it easier to put a dummy task in and advance it so i have a reasonable time window to work in. Also find the way it collapses back on it self is a little harsh as you (i do) tend to fight it when setting the end date.

Robert
 
Thanks Robert.

I would regard it as a bug really, as it makes using it extremely difficult. A ninja's been in touch now, and I've sent him some videos of the issue/s. If anyone else wants to take a look they're here (10Mb).

Mark
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Changing task into project Vinho OmniFocus 1 for Mac 3 2012-06-14 07:37 AM
how to have exact effort durations? it keeps changing them. mlevin777 OmniPlan General 1 2010-11-30 10:33 AM
Changing the duration of tasks by dragging kotoko OmniPlan General 1 2009-10-21 02:53 PM
Inbox: changing a task to a project Paul Hoadley OmniFocus 1 for Mac 12 2008-10-23 07:31 AM
Changing of Task Order only syncs one way? santra OmniFocus Syncing 1 2008-08-06 05:08 PM


All times are GMT -8. The time now is 12:09 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.