Here is a little trick that I used tonight that might be helpful. While reviewing my project list, I realized that many projects had 2 minute NA's holding up progress. OF is brilliant and I continue to find new features. I command+clicked on all of my 2 minute actions and then changed the estimated hours field in the action inspector. Then I created a perspective that showed NA's with a duration of less than 5 minutes. It was fabulous to rip through 20 NA's. I'm going to make this a part of my weekly review.
 
that is a really cool tip ! thanks for sharing that .. I'm adding it to daily review [when possible ] right alongside " verify next actions exist " : )
 
This is a fabulous tip.

But what are NAs? And how do I set durations?

I'd really like to implement this, so that I can set easy tasks to 5 mins and then set up a Perspective for 5 mins. and under.

--Sandy Santra
 
Quote:
Originally Posted by santra View Post
But what are NAs?
Next actions.

Quote:
Originally Posted by santra View Post
And how do I set durations?
Go to Preferences and select the extra column "Extimated Hours."
 
OK, cool. So with Library selected on the left, and the View set to Duration 5 mins., on the right I see only those tasks that are that length or under. Unfortunately, I also see all the other projects (but with no tasks listed). Any way to hide them and just show a list of the projects with tasks 5 mins. and under (and the tasks, of course)? Some of these (maybe all) are empty projects, so maybe what I need is some way not to show empty projects in a view. Thanks.

Last edited by santra; 2007-09-30 at 09:38 AM..
 
Quote:
Originally Posted by santra View Post
OK, cool. So with Library selected on the left, and the View set to Duration 5 mins., on the right I see only those tasks that are that length or under. Unfortunately, I also see all the other projects (but with no tasks listed). Any way to hide them and just show a list of the projects with tasks 5 mins. and under (and the tasks, of course)? Some of these (maybe all) are empty projects, so maybe what I need is some way not to show empty projects in a view. Thanks.
Not in Planning Mode.

Try it in Context Mode.
 
That's it. Thanks!
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
GTD: Things that take more than 2 minutes jonhendry Applying OmniFocus 2 2011-06-26 01:30 PM
Minutes become months in duration hagboe OmniOutliner 3 for Mac 6 2008-08-28 12:42 PM
Duration by Minutes danlavie OmniPlan General 1 2008-07-28 09:23 AM
Zooming in on minutes mjuengling OmniPlan General 3 2006-07-28 03:31 AM


All times are GMT -8. The time now is 12:16 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.