I have a perfectly good critical path going from project start to finish. If I try to explicitly insert reserve into a grouped task then the critical path won't display back from the task to which I add reserve nor will it display within the grouped task's subtasks.
I imagine there is some logic in the critical path disappearance - after all if I've got reserve then those tasks can't be on the critical path? But then I'd expect another critical path to appear but none does.
Still, it is not what I'd expected. I add reserve, I expect the critical path to remain. Am I wrong?
I imagine there is some logic in the critical path disappearance - after all if I've got reserve then those tasks can't be on the critical path? But then I'd expect another critical path to appear but none does.
Still, it is not what I'd expected. I add reserve, I expect the critical path to remain. Am I wrong?