Moving a task and all his content Thread Tools Search this Thread Display Modes
Hi there,

I'm testing OmniPlan we bought a few month ago.

I used it to build a schedule for a main task including dozens of sub-task and sub-sub task. As we have a change of plan, i'm trying to move the main task (drag&drop or change the start date in the Task Inspector. The main task is moving to the date i specify but all the other element keep their initial date.

No way i move them one by one !

What did i have missed ?

Bernard
 
How are you interconnecting the tasks? If you have three tasks one after another, and you move the start date of the first one, the others will not necessarily be rescheduled unless there are dependencies set up.

An example:



I level the resources:



Now I move the start date of the first block out a few days and level again:



The following tasks don't get moved back in time because there is not a Finish->Start dependency between the first one and the subsequent ones. That means the other tasks can be scheduled to start as soon as resources permit. Notice how Task 8 gets started but not completed, as the big first task has a higher priority in scheduling as it appears first in the list. When it finishes, then the remainder of Task 8 can be done.

If you add Finish->Start dependencies to the tasks so that Task 1 must finish before Task 2 starts, and Task 2 must finish before Task 3 starts, then level again, you get this:



and moving the start date of the first task will automatically move the whole schedule that depends ultimately on that first task. You want to set as few dates as possible, because they won't be automatically updated as the schedule changes. If you set the start date on some task to 1 week from today because that's when you "know" that a resource will be finished with the previous task, and then it turns out that estimate was wrong and the resource is available days earlier, you'll have to adjust the start date(s) on that resource's tasks or have it sit idle. The program can do the most for you if you express the constraints on the scheduling with dependencies rather than hard-coding all sorts of dates (which invariably need to be changed!)
 
Hi whpalmer4,

Great i have understood dependency on creation.

But what i'm missing is how i change a task or a group of task dependencies after the tasks have been made. Also i have several level and sublevel. This is an example of one of the simpliest doc i have.



My point is to move the first task [learning mode] and that everything is move with it... now that it is done. :)
 
To add the dependencies, you simply select the items and click the Connection button in the toolbar (hold the mouse button down to get a pop-up menu offering you the different varieties besides the usual Finish->Start).

If you haven't watched them, I highly recommend the video tutorials available at the OmniFocus product page: http://www.omnigroup.com/application...lan/tutorials/
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Moving Single Instance of Repeating Task? MattSharp OmniFocus 1 for Mac 1 2012-05-05 08:19 AM
Questions about the content.xml. Dex OmniFocus Extras 19 2009-04-04 05:03 PM
Moving cursor in task title remedy5 OmniFocus for iPhone 7 2009-01-28 04:40 PM
Indenting (Moving Right) Tasks below another task Phi OmniFocus 1 for Mac 2 2008-09-04 06:38 PM
Locked task and moving tasks issues. michaelklouda OmniPlan General 1 2006-08-01 04:44 PM


All times are GMT -8. The time now is 11:25 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.