In my project plans, I often need to allow a customer some number of days to review a deliverable. The review may take 2 hours, but we often need to allow them three working days to accomplish it. How do I set effort and duration to account for this, so that:
* the effort comes out right in reports (2 hours)
* we allow three days for its completion, and
* if the task is actually completed in 1 day, our revised project plan can account for that?