Hi there,
I'm testing OmniPlan we bought a few month ago.
I used it to build a schedule for a main task including dozens of sub-task and sub-sub task. As we have a change of plan, i'm trying to move the main task (drag&drop or change the start date in the Task Inspector. The main task is moving to the date i specify but all the other element keep their initial date.
No way i move them one by one !
What did i have missed ?
Bernard
I'm testing OmniPlan we bought a few month ago.
I used it to build a schedule for a main task including dozens of sub-task and sub-sub task. As we have a change of plan, i'm trying to move the main task (drag&drop or change the start date in the Task Inspector. The main task is moving to the date i specify but all the other element keep their initial date.
No way i move them one by one !
What did i have missed ?
Bernard