2 dependencies in the same task Thread Tools Search this Thread Display Modes
How can I create FF and SS between same pair of tasks. When I add FF then SS will gone. Vice Versa.
 
To make it clearer, I need Ladder dependency type

Last edited by Kimsake; 2008-05-12 at 05:43 AM..
 
This isn't directly possible. One work-around would be to create an intermediate milestone. So as an example, for the start dependency you'd go A->C->B, and for the end dependency you could go straight from A->B.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Task Dependencies - Must start at commencement of another task matthewforsyth OmniPlan for iPad 2 2013-03-27 02:19 AM
What is a aunt task / Relationship & assigning dependencies with parent/child tasks qubit OmniPlan General 2 2012-09-04 12:16 PM
Dependencies, seems challenging iamhim OmniPlan General 4 2012-08-29 07:51 PM


All times are GMT -8. The time now is 11:50 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.