variable duration for fixed Effort Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Hi all,

I havent found a way to do the following:
I enter a task and assign an effort of - say - 96 hours to it.
(I have no resources in the project by now)
I would then like to also assign a duration to that task without affecting the effort.
So basically I want to tell omniplan: "this tasks requires 96 mh and we will carry it out during the next 2 months"

Havent found that option by now.
What am I missing ?

Thanks in advance

Heiko
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixed Cost, Fixed Duration, Flexible Effort/Resources metasim OmniPlan General 2 2012-02-03 04:24 PM
Fixed duration with varying effort Bijan Parsia OmniPlan General 5 2008-11-07 12:50 AM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM
effort/duration toddbg OmniPlan General 1 2006-09-05 11:05 AM


All times are GMT -8. The time now is 05:52 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.