Hi there, new OP user and what a relief compared to other programs ! ;-)
I have a resource who is working part-time until Christmas, full time starting January. I have combed the OP forums for a more efficient solution than manual entry.
I know I can do this with manual entry by:
- setting the normal work week for this resource for half time until December
- changing the work schedule for this resource to full time manually week by week by week after December
- or of course, the other way 'round.
So, is there a more 'automatic' way to set availabilities of resources across periods longer than a week:
- either by varying their work week over a longer period rather than week by week?
- by varying their availability in "effort conversion factors" by date ?
Thank you !
I have a resource who is working part-time until Christmas, full time starting January. I have combed the OP forums for a more efficient solution than manual entry.
I know I can do this with manual entry by:
- setting the normal work week for this resource for half time until December
- changing the work schedule for this resource to full time manually week by week by week after December
- or of course, the other way 'round.
So, is there a more 'automatic' way to set availabilities of resources across periods longer than a week:
- either by varying their work week over a longer period rather than week by week?
- by varying their availability in "effort conversion factors" by date ?
Thank you !