Lead time is a function of resource schedule? Thread Tools Search this Thread Display Modes
I have observed the following:

If I have a task for which there are no workers assigned, then the lead time to a subsequent task works the way it should. If I set a lead time of 1w between two dependent tasks, then the arrow linking the two extends out for one week before connecting to the dependent task.

However, if I assign a worker (resource) to the first task and that worker does not have a 8 hour/day work schedule, then the lead time mysteriously scales as a function of the number of hours that resource can work. For example, if I put a lead time of 1 day between two tasks, and the first task has a worker assigned to it that works 1 hour per day, then the lead time to the next task will extend out for 8 days.

Is this a bug? If not, how do I get the lead time to be "absolute" lead time?

Thanks!
 
Quote:
Originally Posted by tbrekken View Post
I have observed the following:

If I have a task for which there are no workers assigned, then the lead time to a subsequent task works the way it should. If I set a lead time of 1w between two dependent tasks, then the arrow linking the two extends out for one week before connecting to the dependent task.

However, if I assign a worker (resource) to the first task and that worker does not have a 8 hour/day work schedule, then the lead time mysteriously scales as a function of the number of hours that resource can work. For example, if I put a lead time of 1 day between two tasks, and the first task has a worker assigned to it that works 1 hour per day, then the lead time to the next task will extend out for 8 days.

Is this a bug? If not, how do I get the lead time to be "absolute" lead time?

Thanks!
Hmm, not sure if this is a bug, but I can see how it could be confusing to users who are expecting a different behavior. I'll file a bug report with your findings and we'll check this out ASAP.

Thanks!

Last edited by skwirl; 2007-12-17 at 10:33 AM..
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Need advice re: how to schedule material resource. Thanks! nathanmeffert OmniPlan General 0 2013-05-02 07:19 AM
How does lead time work? nathanmeffert OmniPlan General 1 2010-07-09 01:58 PM
Auto Lead Time stephenrussett OmniPlan General 2 2010-02-16 07:04 PM
About Lead Time vitoraugusto OmniPlan General 0 2010-01-07 03:24 PM


All times are GMT -8. The time now is 08:54 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.