Hello everyone. I'm half experienced with project management concepts, and
I'm in trouble trying to figure out the right way to put this cenario in my project plan:
The case is like this:
I have 2 tasks:
1.1 - Search for image references
1.2 - Keywording* of the selected images
The issue is that "1.1" is a 8h task, that happens weekly, and "1.2" is a 2h task that has to be done every time "1.1" is completed.
As I know, 1.1 can be called a recurring task and 1.2 is dependent from 1.1.
How can I represent this in my plan?
thanks for help!
------------------------------------
* For the ones who are not familiar with the term "keywording":
Keywording = The practice of selecting the most appropriate keywords to describe an object, image, or work.
I'm in trouble trying to figure out the right way to put this cenario in my project plan:
The case is like this:
I have 2 tasks:
1.1 - Search for image references
1.2 - Keywording* of the selected images
The issue is that "1.1" is a 8h task, that happens weekly, and "1.2" is a 2h task that has to be done every time "1.1" is completed.
As I know, 1.1 can be called a recurring task and 1.2 is dependent from 1.1.
How can I represent this in my plan?
thanks for help!
------------------------------------
* For the ones who are not familiar with the term "keywording":
Keywording = The practice of selecting the most appropriate keywords to describe an object, image, or work.