Apologies for this if it's covered elsewhere, I did look but could not find it.
I'm looking to move away from MS Project and so am using Omniplan to create simple/medium project schedules for multiple projects we have going on.
However, I think I've noticed something a little concerning. The effort for individual tasks does not look like it is summing correctly into the summary/group tasks.
It's quite possible I'm missing something, but I opened a new schedule to recreate the issue and added some simple tasks to it and the same issue occurred. I didn't do anything special other than add some individual tasks into the group, then delete them.
I have a screenshot I'll look to upload somewhere and make available.
Thanks
I'm looking to move away from MS Project and so am using Omniplan to create simple/medium project schedules for multiple projects we have going on.
However, I think I've noticed something a little concerning. The effort for individual tasks does not look like it is summing correctly into the summary/group tasks.
It's quite possible I'm missing something, but I opened a new schedule to recreate the issue and added some simple tasks to it and the same issue occurred. I didn't do anything special other than add some individual tasks into the group, then delete them.
I have a screenshot I'll look to upload somewhere and make available.
Thanks