Mixed tasks for same resource Thread Tools Search this Thread Display Modes
I'd like to have some advice on how to achieve the following:

In a simple project, there are 2 tasks, each taking 3 days of work.
There is only 1 resource, which is assigned to the 2 tasks.

After assigning, the resource is overallocated (200%) so I have to level the project.

The result is that the first task in my list will be handled before the second task giving my resource 6 days of work. The first 3 days on task #1 and the following 3 days on task #2

My question:
How can I obtain that my resource will work on BOTH tasks for 50% during 6 days?
 
Quote:
Originally Posted by Archemedia View Post
I'd like to have some advice on how to achieve the following:

In a simple project, there are 2 tasks, each taking 3 days of work.
There is only 1 resource, which is assigned to the 2 tasks.

After assigning, the resource is overallocated (200%) so I have to level the project.

The result is that the first task in my list will be handled before the second task giving my resource 6 days of work. The first 3 days on task #1 and the following 3 days on task #2

My question:
How can I obtain that my resource will work on BOTH tasks for 50% during 6 days?
You can select the task, bring up the "Task : Assignment" inspector, and change the percentage to 50% of 100%. Do this for the other task and you'll be smooth sailing. :-)
 
Quote:
Originally Posted by akwong View Post
You can select the task, bring up the "Task : Assignment" inspector, and change the percentage to 50% of 100%. Do this for the other task and you'll be smooth sailing. :-)
Great, now, is there some support for more complicated operations? I have the same issues but I want to say, "Both occur over this period and end at the same time." i.e. simultaneously. But, one task takes 25w and another takes 4w. Sure, I can manually calculate the percent but is there an automated way?

i.e. 25/29 ~= 86% and 4/29 ~= 14%

Or, is there a way to say, "50% of your time on X and the rest on the remaining projects?"

Last edited by cwingrav; 2009-03-06 at 08:01 AM..
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Automatically assign a resource to new tasks? psidnell OmniPlan General 2 2012-03-28 10:09 PM
Mixed units for durations SteveH OmniPlan General 3 2011-08-20 08:59 AM
Mixed midpoints? macktheturtle OmniGraffle General 1 2007-05-27 03:47 PM
Moving tasks in resource view...? jdrogers@mac.com OmniPlan General 1 2007-01-08 04:37 PM


All times are GMT -8. The time now is 01:49 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.