I've got this scenario: I have a milestone called Project Finished which moves around based on its dependencies. I'd like to have a QA task that has a fixed duration (6w) that needs to start as late as possible, finishing at the same time as my Project Finished. Is this possible? I've only been able to adjust this task manually, moving it forward as the Project Finished milestone moves forward.

thanks
Collin
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Task Dependencies - Must start at commencement of another task matthewforsyth OmniPlan for iPad 2 2013-03-27 02:19 AM
Need to set task to start before another task completes Hugmongous OmniPlan General 1 2012-09-26 01:29 PM
Possible to be reminded to start a task? adnium OmniFocus 1 for Mac 3 2010-07-25 11:57 AM
locking the start of a task immediately upon completion of the previous task mr_projects OmniPlan General 0 2007-10-30 08:12 AM
late to the game.....help! Jeff R OmniFocus 1 for Mac 0 2007-07-22 12:40 PM


All times are GMT -8. The time now is 05:49 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.