Inability to adjust for tasks that are completed ahead of schedule Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I have exactly the same problem as this one, which is the inability to adjust for tasks that are completed ahead of schedule, meaning if i have three tasks:

A, B, C , and im doing task A right now:

A
....B
........C


but if B is done ahead of schedule, when leveling, it ought to look like this :

A
....B
....C

instead of not changing at all


looks to me like its not differentiating between completed tasks and uncompleted ones, Thanks in Advance.

Last edited by mr_projects; 2007-10-30 at 10:25 AM..
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can't Move / Adjust tasks - help! [A: Spotify, VLC, & Rdio for Mac interfere with the mouse] tonyg0192 OmniPlan General 12 2013-01-22 06:18 PM
How do you schedule tasks? J R Applying OmniFocus 9 2010-06-05 05:34 AM
Adjust actual for being ahead of schedule jwhitley OmniPlan General 6 2007-10-11 02:21 PM
Inability to Sync iCal Tasks w/out Context supafly iCal Sync 1 2007-08-19 07:19 AM


All times are GMT -8. The time now is 04:00 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.