I sometimes input tasks with resources and estimated hours for tasks/groups that may or may not occur. For example:

Attempt installation myself. 1h
If installation fails, hire it out
Call contractor and schedule work. 5m
Meet with contractor. 1h

I'm curious if anyone does this any other way, and also it might be interesting to have some if/then logic in a future version of OP, where you could turn on or off tasks or groups, so they don't affect the gantt chart, yet without removing their hours. I may be missing something obvious. thanks

Bob
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Attaching assets to tasks/groups bagleya1 OmniPlan General 2 2012-10-17 08:47 AM
Hierarchical tasks don't appear in Due? [A: Enable "show groups in context mode"] alexp OmniFocus 1 for Mac 3 2012-02-10 10:03 AM
Repeating groups tasks not appearing BarryW OmniFocus 1 for Mac 4 2010-10-30 02:31 PM
Task Groups (and their Tasks) don't show up in Project view Rockyroad OmniFocus for iPhone 15 2010-07-12 01:34 AM
Bug: Groups not reverting to tasks ajrichardson OmniPlan General 9 2006-08-08 12:58 AM


All times are GMT -8. The time now is 01:05 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.