I work in China. They have never heard of a 5 day week, 8 hour day. How do I adjust the days per week from 5 to 7 ?? If I have a container shipping on a Saturday or Sunday I cannot list it on those days ??

Dan

Last edited by danwenke; 2007-07-08 at 09:54 PM.. Reason: not clear enough
 
To change the normal work hours in a week, click on the third button from the left on the toolbar. You should see a calendar with 2 green bubbles. Those bubbles designate when the working hours are. If you simply click and drag the bubbles around, you can make the working hours longer, shorter, or go into the weekends as well.

If you want to set certain off-days like Christmas for example, you can click on the drop down menu on the lower left side of the window and select "Work Schedule for Project". This will allow you to select a specific date on the calendar and set the workable hours for that day.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Repeating Tasks on work week Callen OmniFocus for iPhone 4 2010-08-29 07:55 AM
FR: Tasks repeat/recur on work week schedule dbyler OmniFocus 1 for Mac 6 2010-08-28 08:11 AM
"Work Day Hours" and "Work Week Days" in General Preferences dhm2006 OmniFocus 1 for Mac 2 2007-09-05 01:50 PM
Request: constrain to specified work week mims OmniPlan General 1 2006-10-26 10:47 AM