I'm just starting out with OmniPlan and I'm importing tasks into a new project. However all the dates are starting today. I can't seem to move tasks, for example, three days before today. I've tried removing constraints but when I then try to move the task it just changes the constraint field and the task remains stubbornly at the date set by the import.

Other things I've tried:

1. Reset the system clock (really)
2. Change the task to complete to see if would move (nope)
3. Change the Set Current Editing Date to a week behind today

Nothing seems to work. I'm putting it down to user error but what am I doing wrong?

Thanks.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can't change date for task started before today? [A: Remove constraint in Task:Schedule inspector] chaloum OmniPlan General 11 2013-07-05 12:23 PM
Backdating completed tasks (esp. after rescheduling/leveling) omnibob OmniPlan General 1 2013-02-08 08:34 PM
How to have a task mirror the length of a task group? jamiehale OmniPlan General 1 2011-06-15 07:05 PM
locking the start of a task immediately upon completion of the previous task mr_projects OmniPlan General 0 2007-10-30 08:12 AM
Send Task / Receive Task update by Email samaparicio OmniFocus 1 for Mac 0 2007-07-10 07:58 PM


All times are GMT -8. The time now is 11:38 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.