Task Dependencies - Must start at commencement of another task Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Hey there.

I am working on projects where one task commences immediately as another finishes.

For example,

take cake out of oven - Cook 1 (Resource)
time for cake to cool - No resource

Obviously the cake starts cooling as soon as the previous task starts.

How can I fix the start time of taking the cake out of the oven to the start of the cooling time?
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Need to set task to start before another task completes Hugmongous OmniPlan General 1 2012-09-26 01:29 PM
Start a task as late as possible? cvandyck OmniPlan General 10 2012-09-15 12:33 AM
What is a aunt task / Relationship & assigning dependencies with parent/child tasks qubit OmniPlan General 2 2012-09-04 12:16 PM
2 dependencies in the same task Kimsake OmniPlan General 2 2008-05-16 12:08 PM
locking the start of a task immediately upon completion of the previous task mr_projects OmniPlan General 0 2007-10-30 08:12 AM


All times are GMT -8. The time now is 09:37 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.