How does lead time work? Thread Tools Search this Thread Display Modes
I am a new OmniPlan user. I have two days left on my trial and I am almost sure I'm going to purchase, but have one question that having answer to would really help me decide.

Here's the example:

Day 1: 1) Post ad
Day 2: 2) Check on results day 1
Day 3: 3) Check on results day 2

I want the "Check on results" tasks to fall sometime on the next day. It doesn't matter exactly when, but they HAVE to be on the next day. I used the lead time "+1d" and OmniPlan still schedules the tasks for within the same day quite often (albeit with a large lead time). I really don't understand that.

Any thoughts, comments, or suggestions would be much appreciated!

Thanks in advance,

Nathan

Last edited by nathanmeffert; 2010-07-08 at 09:14 AM..
 
Nathan, I didn't want you to think your question had gone unread, but I must confess that there are other folks at the company with stronger OmniPlan-fu than I possess...

We collectively browse the forums as we are able to do so, but if you need a guaranteed response, you're generally best off if you email the support ninjas.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Work time override? Cassini OmniPlan General 0 2011-07-22 10:23 AM
Auto Lead Time stephenrussett OmniPlan General 2 2010-02-16 07:04 PM
About Lead Time vitoraugusto OmniPlan General 0 2010-01-07 03:24 PM
Lead time is a function of resource schedule? tbrekken OmniPlan General 1 2007-12-17 10:27 AM


All times are GMT -8. The time now is 06:31 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.