Overallocation of resources Thread Tools Search this Thread Display Modes
Is there an easy way to show overallocation of resources? I understand the auto-leveling feature etc, but I'd rather do it consciously in reaction to seeing over allocations. I'm wondering if there is some way that I can get it to show up as a violation or something.
 
Go to the resource view, click on the icon with three little bars of increasing height (underneath the Connection icon in the image below). Now anywhere you see a pink/red blob underneath a task in the right hand side of the window, you've got a resource being overcommitted. When the blue bar doesn't come all the way up to the middle line, you've got a resource being underutilized. If you don't select any of the resources on the left, the view on the right shows all of them, otherwise it only shows the selected resources.

 
Thank you!!
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Time Between Resources scottb OmniPlan General 1 2011-03-31 12:19 PM
non-substitutable resources? tburton OmniPlan General 5 2008-10-01 11:58 AM
allocating resources to me smt OmniPlan General 1 2008-09-18 03:23 PM
Assigned Resources valsjo OmniPlan General 0 2007-10-28 01:26 PM
Import resources? pheski OmniPlan General 2 2007-01-03 07:28 PM


All times are GMT -8. The time now is 10:49 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.