When I set effort to lets say 4d, duration is also set to 4d. So far so good.
When I now ad a resource to this task, the effort stays 4d as expected but the duration is reduced to something like <0.25 h. This probably has to do with resource settings I made but I don't know which. Any suggestions on this one...
Thanks in advance
When I now ad a resource to this task, the effort stays 4d as expected but the duration is reduced to something like <0.25 h. This probably has to do with resource settings I made but I don't know which. Any suggestions on this one...