Duration vs Effort reacts strange Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
When I set effort to lets say 4d, duration is also set to 4d. So far so good.

When I now ad a resource to this task, the effort stays 4d as expected but the duration is reduced to something like <0.25 h. This probably has to do with resource settings I made but I don't know which. Any suggestions on this one...

Thanks in advance
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Decouple Effort and Duration? highcamp OmniPlan General 35 2013-03-15 04:13 PM
Effort not connected to duration bbruck OmniPlan General 1 2008-11-04 05:43 PM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM
effort/duration toddbg OmniPlan General 1 2006-09-05 11:05 AM


All times are GMT -8. The time now is 11:27 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.