Hi, I want to know if it's possible to change the schedule to meet any particular task in the project. I have a project with varying tasks and schedules for each task; for ie. task 1 has a normal schedule of Mon - Fri 8:00 AM - 5:00 and task 2 has a odd schedule of Mon - Fri 8:00 AM - 12:00 PM PLUS Sat 8:00 AM - 2:00 PM. The schedules vary for any given task and I'd like to reflect this in the chart. Currently I don't see this as an option as there is only one master schedule for the entire project. Thanks.