Hi all,

I've setup a group 'software dev team' with 4 members. I've allocated a cost/hour to each member. The cost/hour of the group is the average cost of each member. So far so good.

But if I assign the group to tasks with associated 'effort' values the 'total cost' column remains blank. if i associate the tast to an individual resource i get a correct calculation.

What am i doing wrong?
 
I ran into the same problem and filed a bug report for it a few weeks ago. Apparently this is not yet solved in the 1.1 beta.
 
Thanks for the reports. It's in our database and we've got top men working on it.

-Tom

"Who?" "Top... men."
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Simple Applescript, Create Task, Assign resource, Assign dependency dexterama OmniPlan Extras 2 2012-11-18 01:25 PM
Total cost on task bars in GANT view etvaxed OmniPlan General 1 2012-02-21 07:27 AM
One task, three resources, how do I get an accurate total cost? jimantonopoulos OmniPlan General 1 2011-04-18 11:49 AM
Total Cost for a Resource HunterBoss OmniPlan General 6 2007-07-13 03:01 AM
Showing total resource cost for task groups? docswab OmniPlan General 4 2007-01-04 05:03 PM


All times are GMT -8. The time now is 04:55 PM.