Hi all,
I've setup a group 'software dev team' with 4 members. I've allocated a cost/hour to each member. The cost/hour of the group is the average cost of each member. So far so good.
But if I assign the group to tasks with associated 'effort' values the 'total cost' column remains blank. if i associate the tast to an individual resource i get a correct calculation.
What am i doing wrong?
I've setup a group 'software dev team' with 4 members. I've allocated a cost/hour to each member. The cost/hour of the group is the average cost of each member. So far so good.
But if I assign the group to tasks with associated 'effort' values the 'total cost' column remains blank. if i associate the tast to an individual resource i get a correct calculation.
What am i doing wrong?