when i drag a task bar to the left i sometimes get a grey bar appearing and the task stops moving, the grey bar continues. i know have some tasks with long grey bars before them to the left. im editing actuals.

what is this? been looking in the help and cant find anything

thanks
 
Does it look like this?



The grey bar indicates a constraint. You can drag them out by holding down the shift key and dragging on the end of a bar in the Gantt chart, or set them through the Inspector.
 
thanks. not really sure how they got added. ive deleted the constraints in the task inspector and now they are gone. i imported my plan from a demo of merlin so maybe it got added in there somehow?
 
There was a post on the OmniPlan 2 private beta forum that might be enlightening, too. I hope Tom doesn't mind my taking the liberty of reposting his message!

Quote:
Originally Posted by Tom Bunch
The "grey-box-extensions", don't indicate any kind of conflict. Think of them like a trough. If you set both a start and end constraint on a task, OmniPlan can feel free to slide the task anywhere within the trough without causing a violation. Leveling and explicit dependencies are two things that will go ahead and do that.

In 1.x, when you moved a task, group or milestone start date, you are changing the scheduling method of the item to "On specified date". Thereafter leveling will not move the task. We found that when people start with OmniPlan they create tasks, start dragging them around to get a sense of the project, do some resource assignments, and then try leveling, which they very reasonably assumed was completely broken when it didn't move tasks.

That informed our thinking that when they start dragging tasks like that, they're really saying, "don't start that until somewhere over here" and what they really want is a start constraint.

To that end, I think we really need to support start constraints on groups and implicitly set them if the project date is earlier than today. Group start constraints do constrain the child tasks, and you can add an empty group at any time.

I think your use of the term "split" may be confusing me, given that we now support true split tasks. If you take a project starting some days ago, add a task (automatically constrained to start today) drag it to tomorrow, and add a child task to it (automatically constrained to start today), the first task will be constrained to start at whatever point you dragged it to, and the child task will have an earlier constraint that busts right out of the group's bounding rectangle (see View -> Gantt -> Group Shading). Is there a specific part of those results that is troubling?

-Tom
A comment about dragging things around: in my opinion, it is best to express the structure of your plan with dependencies, lead times, and constraints as needed, trying to do as little fixed assignment of what happens when as possible (in other words, "this needs to happen after this task finishes" is good, and "this needs to happen on Tuesday" is not good, unless it really has to happen on Tuesday, and you aren't just saying that because you expect the previous thing will take all of Monday). This gives OmniPlan the most flexibility to find good solutions when leveling, and also helps you if you decide to move the whole project.
 
Quote:
Originally Posted by whpalmer4 View Post
There was a post on the OmniPlan 2 private beta forum that might be enlightening, too. I hope Tom doesn't mind my taking the liberty of reposting his message!
Beta forums got marked private because we didn't want to confuse new folks that came to the forums after the final release. No problem posting material from them, though, and we're happy to resurrect threads/posts/material from them upon request. :-)
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Formatting Task Bars... Alohajoe5 OmniPlan General 0 2012-08-04 11:25 AM
Total cost on task bars in GANT view etvaxed OmniPlan General 1 2012-02-21 06:27 AM
Unable to drag task bars in Gantt view jtwms1 OmniPlan General 8 2010-12-26 09:04 AM
Grey display Manticore OmniGraffle General 3 2006-05-20 03:03 AM


All times are GMT -8. The time now is 12:22 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.