The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
Tasks are not changing as expected with leveling Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I have a resource assigned to 6:30 pm to 9:30 pm schedule and another one with the same availability.

One task that requires both will take 3 hrs to complete, another will take 2 hrs.

However, OmniPlan is scheduling the tasks for mid-afternoon starting at 2:30.

This makes no sense. I've double checked assignments and schedules and re-leveled.

Any ideas? Thanks in advance!
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Backdating completed tasks (esp. after rescheduling/leveling) omnibob OmniPlan General 1 2013-02-08 08:34 PM
Difficulty Splitting Tasks During Leveling morricej OmniPlan General 4 2012-02-14 06:53 AM
Leveling ignores completed tasks jelliot OmniPlan General 6 2011-09-08 02:51 PM
Issues with leveling constrained tasks bjamison@exacttarget.com OmniPlan General 1 2007-11-09 04:30 PM
Leveling of short duration tasks bgeipel OmniPlan General 3 2007-11-09 08:58 AM


All times are GMT -8. The time now is 05:09 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.