Adding resources makes task take longer? Thread Tools Search this Thread Display Modes
I have a task that I assigned 3 days as the effort needed. Then, as I assign resources to this task, it takes longer and longer to complete. With two people working 70% I have 1w 2.75 hrs.

What kinda' of things could I be doing wrong to make it behave like this?

Many thanks in advance.

-jim lee
 
It's hard to tell for sure just from your description. If you start with a 3 day (effort) task and assign one person at 70%, then the task will take longer, because that 3 day effort means 1 person working at 100% for 3 days.
However, once you add a second person at 70%, it should get shorter again. Perhaps you could send your file to our Support Ninjas to take a look? If you use the "Send Feedback" command in the Help menu, it can automatically create a version of your file with your task names and other potentially private data replaced with generic data like "Task 1" and "Resource 4".
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
One task, two resources, different hours Bridgeblox OmniPlan General 8 2013-03-15 02:57 PM
Adding multiple resources to a task without changing duration blaketime OmniPlan General 5 2011-10-04 11:57 AM
How About Adding Time Zone Specification for Resources? FrustyCronch OmniPlan General 3 2009-11-17 02:20 PM
2 resources on the same task edasque OmniPlan General 1 2006-08-03 12:46 PM


All times are GMT -8. The time now is 01:03 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.