Critical Path Broken with Grouped-Task Reserve Thread Tools Search this Thread Display Modes
I have a perfectly good critical path going from project start to finish. If I try to explicitly insert reserve into a grouped task then the critical path won't display back from the task to which I add reserve nor will it display within the grouped task's subtasks.

I imagine there is some logic in the critical path disappearance - after all if I've got reserve then those tasks can't be on the critical path? But then I'd expect another critical path to appear but none does.

Still, it is not what I'd expected. I add reserve, I expect the critical path to remain. Am I wrong?
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Critical Path - won't highlight path aboeing OmniPlan General 4 2014-04-09 12:49 PM
Critical Path Question stephenrussett OmniPlan General 7 2010-02-16 04:56 PM
Critical Path and Task Dates anthoj OmniPlan General 2 2009-09-18 10:17 AM
Critical Path MacBerry OmniPlan General 11 2009-03-15 07:36 AM


All times are GMT -8. The time now is 01:19 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.