The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniFocus > OmniFocus 1 for Mac
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
task groups [sub-projects ] are automatically sequential ?? Thread Tools Search this Thread Display Modes
I've noticed that any task groups or " sub projects " are automatically sequential ? The tasks below the next action are all grayed out .
It appears this can't be changed by the inspector because it's following the preference of the " parent " project ?
 
You can change an action group from sequential to parallel by right-clicking on it and selecting parallel from the context menu that pops up. This is not the ideal interface (as has already been discussed in another thread), but I would expect Omni to clean it up before the final release of OF.
 
oh that's cool . I missed that somehow .. works for me !

thanks again : )
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Task groups, and sequential work omnibob OmniPlan General 2 2012-02-10 03:30 PM
Parallel vs Sequential Action Groups masoric OmniFocus for iPad 2 2010-10-02 06:47 AM
Action Groups Don't Get Marked as Done Automatically minato2 OmniFocus for iPhone 15 2008-11-25 12:39 PM
Shouldn't task get automatically moved to projects? tango OmniFocus 1 for Mac 8 2007-07-29 03:05 AM
should projects (and task groups) be parallel by default? markbrown00 OmniFocus 1 for Mac 10 2007-07-09 12:17 PM


All times are GMT -8. The time now is 06:19 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.