Assign a period of time to work on a task each day Thread Tools Search this Thread Display Modes
Is there a way to assign a period of time to work on a task each day.

I'm trying to allocate resources for a project and would like to schedule some time each day to use a resource.

The idea is that if a have task that takes 5 hours and I work one 1 hour a day on the task, I could schedule the resource so that other project tasks will know the availability of the resource.

Is this possible.

Thanks,

Ben
 
This is a good question that hasn't had a reply, so I'm giving it a bump. I'd like to know if it's possible too.
 
I'm interested also!
 
Quote:
Originally Posted by Ben Greenfield
Is there a way to assign a period of time to work on a task each day.
Not exactly: resources have schedules, but tasks don't.

Quote:
I'm trying to allocate resources for a project and would like to schedule some time each day to use a resource.
One way of approaching this problem would be to split the resource into two resources, one which is available one hour a day and assigned to your five-hour task, and another which is available the rest of the time which you would use for your other project tasks.
 
I would like to see a "maximum hours devoted to task each day" feature.

Creating multiple "virtual resources" to handle this situation (what I understand Ken to be saying) would turn into a nightmare in my project. I've got 15 tasks in the project, with three staff resources handling those jobs over a period of months. Splitting those three staff into multiple staff resources as a workaround would throw off the entire timeline. Especially since some tasks require a staff resource's full time.
 
Quote:
Originally Posted by mprewitt
I've got 15 tasks in the project, with three staff resources handling those jobs over a period of months. Splitting those three staff into multiple staff resources as a workaround would throw off the entire timeline. Especially since some tasks require a staff resource's full time.
While it might be considered a workaround, I've been setting the Assigned Amount for a resource assigned to a task to the level-of-effort being applied to the project by that resource.

So, if I want to commit a resource to "1 hour per day" on a particular task, I assign 12% (of an 8-hour day [approx]) of the resource to that task.

From my preliminary testing, that appears to level as I would expect.

YMMV.
 
Quote:
Originally Posted by alansg
While it might be considered a workaround, I've been setting the Assigned Amount for a resource assigned to a task to the level-of-effort being applied to the project by that resource.

So, if I want to commit a resource to "1 hour per day" on a particular task, I assign 12% (of an 8-hour day [approx]) of the resource to that task.
Thanks, I have experimented with this too, and it seems to show promise of working well. Will need to research it further.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Forecast feature request - assign task to time slot on calendar cbeaudj OmniFocus 2 for Mac (Private Test) 3 2013-04-25 01:09 AM
Simple Applescript, Create Task, Assign resource, Assign dependency dexterama OmniPlan Extras 2 2012-11-18 12:25 PM
Way to calculate duration for a given time period? Dorian OmniFocus Syncing 1 2008-08-31 12:42 PM
Way to calculate duration for a given time period? Dorian OmniFocus 1 for Mac 0 2008-08-31 08:44 AM


All times are GMT -8. The time now is 12:24 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.