Have marked tasks as completed by mistake. Thread Tools Search this Thread Display Modes
I am anew user setting up a new project plan and I have managed to mark most of the tasks as completed by mistake. how can I reverse this so none of the dates are greyed out ?

thanks
 
select the completed tasks you'd like to reverse, then in the inspector and under Task settings, look for "completed" , and change that to 0%, this should make all the tasks selected uncomplete
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Export tasks (including completed tasks) Oakbank24 OmniFocus for iPad 6 2014-02-07 03:04 AM
Can tasks be marked as "Due Soon" when the start date is reached? Flex OmniFocus 1 for Mac 7 2012-10-10 12:05 AM
Why do alerts sound for tasks I've marked completed? WilliamGallagher OmniFocus for iPhone 3 2012-04-05 11:16 PM
Completed Tasks anthoniii OmniFocus 1 for Mac 8 2010-04-22 05:26 PM
Keep completed tasks? darcy.mulder OmniFocus 1 for Mac 2 2008-10-29 04:40 PM


All times are GMT -8. The time now is 03:49 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.