Example:

* I have a monthly repeating task that starts every 1st and is due every 5th.
* This month I can start on the 7th and due on the 10th.
* Next month should not be affected (start 10/1, due 10/5).

Is this possible within OF?

Thanks,

Kyle
 
Yes, if you use a script. See this post: http://forums.omnigroup.com/showpost...41&postcount=2

The script marks the one you want to reschedule as complete, causing OmniFocus to generate the next one at the scheduled time. The script then turns the action marked complete into a non-repeating action, marks it incomplete, and bumps the dates by the amount you requested. If you want to adjust the dates asymmetrically, you'll have to adjust them by hand, but either way, you won't perturb the regular repeat structure.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can't change date for task started before today? [A: Remove constraint in Task:Schedule inspector] chaloum OmniPlan General 11 2013-07-05 12:23 PM
Automatic change of context at some point in future kgoodfellow OmniFocus Extras 1 2012-06-26 08:28 PM
delete repeating todo deletes all future occurrences rllewis@mac.com OmniFocus 1 for Mac 5 2010-10-26 04:45 AM
change effort w/o changing duration juicychus OmniPlan General 2 2007-11-27 02:40 PM
Future tasks--when do they first show up? santra OmniFocus 1 for Mac 1 2007-10-05 09:40 AM