Subtle problem with end constraints Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
The very last item in my plan is scheduled As Late As Possible and has an end constraint. All other things being equal I would expect it to be scheduled so it finishes at it's end constraint time.

Yet when I level the resources it gets rescheduled to several days earlier than it's end constraint for some reason I can't fathom.

However if I add an unrelated milestone to the project at some point in the future beyond the end constraint time above and level, my task is rescheduled to end at it's end constraint time - as I would expect.

This only occurs to the task that is furthest in the future in my project.

Have I misunderstood something?

(Using V2.0.3)

Last edited by psidnell; 2012-04-27 at 11:29 AM..
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
End Constraints matthewforsyth OmniPlan for iPad 1 2013-04-01 05:28 PM
Actual and Constraints tonygoulding OmniPlan General 0 2012-08-22 04:31 AM
Multiple Constraints? bwilder1998 OmniPlan General 1 2012-03-08 12:02 PM
Cascade constraints ali0482 OmniWeb General 0 2010-08-28 03:26 AM
Constraints rroskelley OmniPlan General 8 2008-12-08 09:59 PM


All times are GMT -8. The time now is 09:19 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.