I have a resource (person) that will start out shared between two tasks 50/50. I understand that this extends each effort out 2x for that person and they'll be listed as 50% on each. I have no problem setting this up in OmniPlan.

But, how do I track that person changing to full time on the second of the two projects when the first one completes? If I set the person at 50% on both, he'll still be constrained to 50% even when the first project ends and he should jump to 100%.

Specifically, how do I manage resource C, below?

I could split the task into slices, but then that complicates assigning other resources. I'd prefer it if I could tell Omniplan whether to prefer to share a resource across projects, or to serialize their efforts by prioritizing a project.

 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Shared templates d2hamilton OmniOutliner for iPad 4 2012-02-29 09:18 PM
Shared collaboration? tbarbe OmniGraffle General 0 2010-09-03 11:44 AM
Shared Stencils borahm OmniGraffle General 0 2010-08-03 12:21 AM
EMail folder dedicated for tasks JackTB Applying OmniFocus 0 2010-06-25 10:33 AM
shared layers kajtzu OmniGraffle General 2 2009-09-24 08:45 AM


All times are GMT -8. The time now is 04:25 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.