When a week isn't a week Thread Tools Search this Thread Display Modes
I'm using OmniPlan 1.1.2 and have a project's default calendar to use a work week of 7 days (instead of the usual M-F 5 days). However, when I assign effort of 5 days to a task, it becomes 1w instead of staying at 5d. Similarly, a task that is planned for a calendar week (say, Thursday to Thursday) shows up as consuming more than a week.

I'd appreciate any advice how to reconcile the schedule with the effort data.
 
That's in the Project: Formatting inspector. Specifically, you can either make your project have 56 hours per work week (8 per day * 7 days), or you can turn off display of weeks of duration entirely (if you'd prefer to see, say, "8d" rather than "1w 1d").

Hope this helps!
 
Thanks, Greg, that solved my problem.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
What I did last week adrianwi OmniFocus 1 for Mac 3 2010-06-14 08:29 AM
First day of the week? FlyingBarney OmniFocus 1 for Mac 2 2009-05-16 01:52 AM
Due within Next Week? gumby911 OmniFocus 1 for Mac 1 2008-05-07 11:00 PM
Due Next Week...or Whenever julrdrgz OmniFocus 1 for Mac 3 2008-01-18 08:51 PM


All times are GMT -8. The time now is 12:01 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.