I have several finish start dependencies where the second task must be finished 30, 60 or more days after the first.

For example, I need task B to be scheduled 30 days after task A is finished. I do not want to put a hard date in the constraint for task B because the finish date for A may change. I would like the schedule for B to automatically reflect the 30 days from the date that A is actually finished.

How can I do this?
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
End Constraints matthewforsyth OmniPlan for iPad 1 2013-04-01 05:28 PM
Constraints and the working week Spacester OmniPlan General 1 2012-09-05 07:20 AM
Actual and Constraints tonygoulding OmniPlan General 0 2012-08-22 04:31 AM
Multiple Constraints? bwilder1998 OmniPlan General 1 2012-03-08 12:02 PM
Cascade constraints ali0482 OmniWeb General 0 2010-08-28 03:26 AM


All times are GMT -8. The time now is 09:27 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.