Hi, I'm looking for a product able to assign to a task specific calendar.
I'm still in the triyng period with omniplan and despite its very attractive conception I didn't find to way to do what I really need.
Suppose that I have to control on a single file tha planning of consultings activities accros multiple customers (mapped as an high level group of tasks). Some resources will works 2 day a week for one group and 3 days/w for an another task group.
Any suggestions to have an automated split of 10d on a five w shedule two day a week for first group?
Any workaround?
Is it possible to expect such functionality on new releases?
Thanks
I'm still in the triyng period with omniplan and despite its very attractive conception I didn't find to way to do what I really need.
Suppose that I have to control on a single file tha planning of consultings activities accros multiple customers (mapped as an high level group of tasks). Some resources will works 2 day a week for one group and 3 days/w for an another task group.
Any suggestions to have an automated split of 10d on a five w shedule two day a week for first group?
Any workaround?
Is it possible to expect such functionality on new releases?
Thanks
Last edited by TesterConsulting; 2011-01-29 at 06:46 AM..