The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
How to have a task mirror the length of a task group? Thread Tools Search this Thread Display Modes
I have a big list of tasks that lasts for say a year, but will change as I change the tasks. I have another task, call it project management, that needs to start when the big list of tasks starts, and end when it ends.

I want one management task that lasts as long as the total of the work tasks, and I don't want to have to manually update it as the work tasks change during planning.

1) Is this a reasonable thing to do? Or is there a better way to organize things?
2) If it's reasonable, how do I do it?

Thank you.

J

Last edited by jamiehale; 2011-06-15 at 07:42 PM.. Reason: Clarification
 
Unless I am mistaken, that sounds like OmniPlan 2.0’s "hammock" task feature.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Split task or group? amarkelo OmniPlan General 2 2013-04-01 05:08 PM
Add task to group of action Martino OmniFocus 1 for Mac 1 2013-02-01 10:04 AM
Group end and Task end issue stephenrussett OmniPlan General 0 2010-02-21 12:09 PM
Task length during drag-and-drop santra OmniPlan General 0 2009-01-09 01:07 PM
Simple question about task length change santra OmniPlan General 1 2008-03-13 03:46 PM


All times are GMT -8. The time now is 08:00 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.