Hi All,

Is it possible to add a milestone that will be complete 2 weeks after a prerequisite task?

e.g. I'm tracking a game I'm making on the AppStore and know that the waiting time for approval for updates is currently 14 days... I'd like to add a 14 day waiting time to the end of any tasks I do before an update submission so I'll know when the earliest time I should be able to submit a new update...

Is that possible with milestones?

Thanks!
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Milestone / Task Tolerance smarsh OmniPlan General 3 2011-02-19 04:05 PM
Waiting context vs waiting project status? marshallj OmniFocus 1 for Mac 3 2009-04-13 02:49 PM
Milestone Formatting? lally OmniPlan General 1 2006-11-06 05:13 PM


All times are GMT -8. The time now is 04:22 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.