The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
resource management Thread Tools Search this Thread Display Modes
Is there a way to disable the percentage of labor feature for resource management? For my project it is possible to have a single person working on multiple tasks simultaneously, and it becomes tedious to change everyone's units of labor to 50% every time overlap occurs.
 
The best way I could figure out to do this was have each person on the project categorized as a material so that it doesn't matter if they overlap. It works, but now there is no difference between staff and materials. Interesting social commentary? :-)
 
You can also set the unit percentage of each resource in the "Resource : Information" inspector to a huge number so that you never reach the resource's overload percentage.
 
Thanks! That is so useful
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource management as a project or context Aniseedvan Applying OmniFocus 2 2012-05-10 02:44 PM
Resource shared in two 'resource groups' t-awesome OmniPlan General 1 2010-05-11 04:51 PM
Project resource management workflow tip colicoid OmniFocus 1 for Mac 1 2008-03-24 01:54 PM
Export selected resource in Resource View upriser OmniPlan General 3 2008-03-05 06:25 AM


All times are GMT -8. The time now is 03:53 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.