Hi folks:

As I have recently moved from a PC to Mac, I've just begun evaluating OminPlan and can't seem to figure out what should be simple.

Let's say I've entered all the tasks and duration info in a project, but now I want to start the project on a different day. Is there any way to select all the tasks and move them without messing with the dependency functions?

Thanks.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Move entire project to new end date dannyw OmniPlan General 5 2011-12-14 09:24 AM
fit the Entire Project into one page onqun OmniPlan General 1 2009-09-14 09:31 PM
Rescheduling uncompleted work... coreyjenks OmniPlan General 1 2008-05-20 01:20 PM
Do Actions On hold force the entire Project to be On Hold? MarkSealey OmniFocus 1 for Mac 2 2008-02-26 06:27 AM
Rescheduling a group of tasks kwispel OmniPlan General 3 2007-12-17 02:09 PM