I set up my projects and then hit level - Omniplan moved everything around and has me starting on task #1.1.4 rather than #1.1.1.1
Since I had already started 1.1.1.1 and 1.1.1.2 I finished those and marked them as complete - hit level again thinking it would rearrange my project to best make use of the rest of the day and start fresh on the other tasks.
However it did not. Omniplan still has my completed tasks and the milestone associated with it as being scheduled two weeks out, with me starting other tasks this morning.
How can I correct this? am I expecting something different than what level does?
Thanks
Since I had already started 1.1.1.1 and 1.1.1.2 I finished those and marked them as complete - hit level again thinking it would rearrange my project to best make use of the rest of the day and start fresh on the other tasks.
However it did not. Omniplan still has my completed tasks and the milestone associated with it as being scheduled two weeks out, with me starting other tasks this morning.
How can I correct this? am I expecting something different than what level does?
Thanks